Commissioning Begins as Kiniéro Aims for Q4 Milestone – goldsilverpress

QUEBEC CITY, Quebec, Nov. 17, 2025 (GLOBE NEWSWIRE) — Robex Resources Inc. is making significant strides in the development of its Kiniéro Gold Project in Guinea, West Africa. With the commissioning and operations team fully mobilized on-site, the company is on track to achieve its goal of producing its first gold by the fourth quarter of 2025. This article delves into the latest updates from the project, highlighting key milestones and future prospects.

Project Milestones

Mobilization and Initial Operations

Robex has successfully mobilized its mining contractor fleet, marking a crucial step in the project’s development. The first ore has already been delivered to the Run-of-Mine (ROM) pad, setting the stage for subsequent processing. This initial delivery is a testament to the efficient planning and execution by the Robex team, which is committed to maintaining a safe and methodical approach throughout the project.

Grade Control and Infrastructure Development

The completion of grade control drilling over the Sabali pit is another significant achievement. This drilling is essential for ensuring that the ore extracted meets the expected quality standards, which is critical for the efficiency of the processing plant.

In addition, the tailing storage facility is nearing completion and is expected to be ready for ore commissioning soon. This facility is vital for the safe disposal of waste materials generated during the gold extraction process, ensuring compliance with environmental regulations.

Power and Electrical Systems

The installation and testing of the power station engines have been completed, with preparations underway for energization. The electrical and pre-commissioning activities for the process plant are progressing according to schedule, which is crucial for the timely commencement of operations.

The high-voltage switchgear has also been pre-commissioned and is ready for testing, with energization planned for this week. This infrastructure is essential for managing the electrical supply to the plant, ensuring that operations can run smoothly and efficiently.

Communication and Control Systems

A robust communication network has been installed in the process plant, connecting to the plant control system and already energized. This network is vital for real-time monitoring and control of operations, enhancing the overall efficiency and safety of the plant.

The Carbon-in-Leach (CIL) motor control center has been energized, and function testing of the drives has commenced. Additionally, the CIL Train A tanks have been filled with water, preparing them for load testing of the agitators and intertank screens. The SAG mill drive train has also been installed and aligned, with the inching drive energized, paving the way for the ball mill to follow.

Leadership Insights

Matthew Wilcox, Managing Director and CEO of Robex, expressed his satisfaction with the progress made at the Kiniéro project. He stated, “Kiniero is moving closer to completion each month, and it is pleasing to see this progress continue in a safe and methodical manner, maintaining our schedule to achieve first gold in 2025.” His confidence in the project’s trajectory is bolstered by the completion of grade control drilling and the delivery of ore to the ROM pad.

Wilcox emphasized that Robex is fully funded and remains on budget for the completion of the Kiniéro project, reinforcing the company’s commitment to delivering on its promises to stakeholders.

Future Outlook

Robex Resources Inc. is well-positioned to complete the construction of the Kiniéro Gold Project, with first gold production anticipated in Q4 CY25. The company’s strategic planning, efficient execution, and commitment to safety and environmental standards are key factors contributing to its progress.

As the project moves closer to its operational phase, stakeholders can expect continued updates on milestones and developments. Robex’s proactive approach and robust infrastructure development indicate a promising future for the Kiniéro Gold Project, which is set to play a significant role in the company’s growth and the broader West African gold mining landscape.

Conclusion

The advancements at the Kiniéro Gold Project underscore Robex Resources Inc.’s dedication to responsible mining and operational excellence. With critical milestones achieved and a clear path forward, the company is on the brink of a significant achievement in its journey towards gold production. Investors and stakeholders alike will be keenly watching as Robex approaches this pivotal moment in its history.

For more information, please visit Robex Resources Inc. or contact their investor relations team.

Related Articles

spot_img

Latest Articles

bitcoin
Bitcoin (BTC) $ 95,468.58
ethereum
Ethereum (ETH) $ 3,195.01
tether
Tether (USDT) $ 0.999536
xrp
XRP (XRP) $ 2.27
bnb
BNB (BNB) $ 935.20
solana
Wrapped SOL (SOL) $ 141.33
usd-coin
USDC (USDC) $ 0.999981
tron
TRON (TRX) $ 0.292525
staked-ether
Lido Staked Ether (STETH) $ 3,191.13
dogecoin
Dogecoin (DOGE) $ 0.161479
cardano
Cardano (ADA) $ 0.491973
figure-heloc
Figure Heloc (FIGR_HELOC) $ 1.03
wrapped-steth
Wrapped stETH (WSTETH) $ 3,889.82
wrapped-bitcoin
Wrapped Bitcoin (WBTC) $ 95,355.55
whitebit
WhiteBIT Coin (WBT) $ 52.81
wrapped-beacon-eth
Wrapped Beacon ETH (WBETH) $ 3,454.96
zcash
Zcash (ZEC) $ 681.55
hyperliquid
Hyperliquid (HYPE) $ 38.55
bitcoin-cash
Bitcoin Cash (BCH) $ 494.49
chainlink
Chainlink (LINK) $ 14.05
usds
USDS (USDS) $ 1.00
binance-bridged-usdt-bnb-smart-chain
Binance Bridged USDT (BNB Smart Chain) (BSC-USD) $ 0.99985
leo-token
LEO Token (LEO) $ 9.22
weth
WETH (WETH) $ 3,190.48
wrapped-eeth
Wrapped eETH (WEETH) $ 3,445.23
stellar
Stellar (XLM) $ 0.257708
ethena-usde
Ethena USDe (USDE) $ 0.998861
litecoin
Litecoin (LTC) $ 96.59
monero
Monero (XMR) $ 395.69
coinbase-wrapped-btc
Coinbase Wrapped BTC (CBBTC) $ 95,325.54
avalanche-2
Avalanche (AVAX) $ 15.60
hedera-hashgraph
Hedera (HBAR) $ 0.150425
sui
Sui (SUI) $ 1.71
shiba-inu
Shiba Inu (SHIB) $ 0.000009
uniswap
Uniswap (UNI) $ 7.87
polkadot
Polkadot (DOT) $ 2.82
the-open-network
Toncoin (TON) $ 1.85
dai
Dai (DAI) $ 0.999195
ethena-staked-usde
Ethena Staked USDe (SUSDE) $ 1.20
crypto-com-chain
Cronos (CRO) $ 0.112001
usdt0
USDT0 (USDT0) $ 1.00
world-liberty-financial
World Liberty Financial (WLFI) $ 0.147223
mantle
Mantle (MNT) $ 1.19
canton-network
Canton (CC) $ 0.109994
susds
sUSDS (SUSDS) $ 1.07
memecore
MemeCore (M) $ 2.16
paypal-usd
PayPal USD (PYUSD) $ 0.999816
bittensor
Bittensor (TAO) $ 328.87
near
NEAR Protocol (NEAR) $ 2.30
usd1-wlfi
USD1 (USD1) $ 0.999094
en_USEnglish